Eroding ... again

City officials seek state permit to fill in 'hot spot' less than 2 years after renourishment

By Bo Petersen
The Post and Courier
Sunday, April 18, 2010



ISLE OF PALMS--The fix needs a fix.

Less than two years after the Wild Dunes beach was saved in a controversial $10 million renourishment, high tide surf once again crowds the resort's signature oceanfront 18th hole and nearby Ocean Club condominiums. New dunes have been dumped from trucks along the hole in a stop-gap effort to ward off a "hot spot" of erosion.

The erosion scarp is getting cut away by a channel as a huge sandbar creeps toward shore from Dewees Inlet -- an unsettling development for a project that was supposed to last eight to 10 years. City officials are seeking a state permit to scrape sand from sandbars that already have attached to the beach and use it to fill in the hot spot.

photo

The Post and Courier

Sand dunes have been piled up at a 'hot spot' of erosion next to the 18th hole of the golf course at Wild Dunes, where a beach renourishment project has lost 50 percent of the sand that was placed there two years ago.

photo

The Post and Courier

The entire beach renourishment project in front of Ocean Villas at Wild Dunes still has 80 percent of the sand that was placed there nearly two years ago.

It's a temporary fix, to shore up the beach until the offshore sandbar attaches, renourishing the beach on its own.

"They believe they can basically move sand around and fill in that area for a long while," said Mayor Dick Cronin, about the engineers who are monitoring the beach. "Frankly, it's a small volume that needs to be moved. It's the most effective way (to do it)."

The method is called shoal scraping. It's also controversial, and previous city attempts to get permits to do shoal scraping have been opposed, City Council was told at a special meeting on the erosion. A recent report by a state shoreline advisory panel said scraping can "downdrift" some of the remaining sandbar; in other words, knock it loose in the current and keep it from beaching.

Tim Kana, president of Coastal Science & Engineering, the firm running the project for the city, recommended scraping as the most cost-effective way to fill the spot. The scraping should speed up the sandbar attaching itself to the beach, he said in an e-mail. He told council members to expect that getting a permit could take two years.

"We're going to have to look at it in the details" before deciding whether to challenge the permit, said Hamilton Davis, program manager for the Coastal Conservation League, the environmental advocate that fought permits for some of the shoring-up work before the 2008 renourishment.

In the bigger picture, Davis said, shoal scraping is "one more of those solutions that are just gambles. It's a poor land use decision."

The 2008 renourishment was wrenched from two years of legal arm-wrestling between owners and state regulators after tens of thousands of sandbags washed away in storm tides, littering the coast and marshes for miles. The $10 million was paid for largely by Wild Dunes property owners, with tax money paying $3 million.

From the beginning, some opposed using any public money to shore up the private resort -- tax revenue or not.

Hot spots were expected in the unstable inlet area after the 2008 renourishment, and $1 million from that project was set aside to deal with them. The proposed shoal scraping would cost less than that.

Overall, some 80 percent of the renourishment sand is still in place. Along the hot spot, more than half the sand is estimated to still be in place.

Kana said he expects another round of sandbar movement to start in the next few years, "so this is likely a recurring problem -- just as it has been for the past three decades." He's confident the erosion will be a fraction of the erosion that occurred before the project, he said.

Before the 2008 project could get started, half of the green had washed away on the 18th hole, and the Ocean Club had waves washing into its carport. The Ocean Club and nearby condominiums were facing condemnation. The erosion this time cut close enough to the hole and the Ocean Club by March that the owners of both asked for state permits to dump the truck sand. But at low tide the beach is still wide.

"We're not particularly alarmed at this point," said Carl Harper, of the Ocean Club. "It appears the beach is renourishing itself."

Reach Bo Petersen at 937-5744 or bpetersen@postandcourier.com.

Share this story:
E-mail this story E-mail this story  Printer-friendly version Printer-friendly version  

Copy and paste the link:

Add this

Comments

Use the comment form below to begin a discussion about this content.

Notice about comments:

Postandcourier.com is pleased to offer readers the enhanced ability to comment on stories. We expect our readers to engage in lively, yet civil discourse. Postandcourier.com does not edit user submitted statements and we cannot promise that readers will not occasionally find offensive or inaccurate comments posted in the comments area. Responsibility for the statements posted lies with the person submitting the comment, not postandcourier.com. If you find a comment that is objectionable, please click "report abuse" and we will review it for possible removal. Please be reminded, however, that in accordance with our Terms of Use and federal law, we are under no obligation to remove any third party comments posted on our website. Read our full Terms and Conditions.

Users can now build user-to-user connections, follow friends' recent posts, add an avatar that fits their personality, and more. If you have posted here before you'll need to sign up again, or if you've never posted before, start now by signing up!


 

Most Popular

 

Sponsored Links